M. Nielbock; 13-Nov-2007
Index TableOfContents(2)
1. IST Chopper Day at Astrium (2007-11-13)
According to Sect. 11 of the PACS IST Procedure Document (PACS-ME-TP-021, Issue 2.5), we will verify the functionality of the PACS chopper during an especially dedicated "Chopper Day" during FM-IST at Astrium. This includes three steps for both the nominal and redundant operations. The CUS scripts are the same for both parts; we will adjust the suitable chopper control parameters by editing and uploading the referring CALU table.
1.1. Chopper Zero-Point Offset Nulling
- combined with SFT open-loop measurement
- used as input for new configuration table
1.2. Verify Stability of the Chopper
The command sequence is:
- WriteOBSID_ast_OBS
- CONF_chopper_ast_OBS_Shell
PACS_Chopper_EnDis_Test_ast1_OBS_Shell
- CONF_chopper_ast_OBS_Shell
PACS_Chopper_EnDis_Test_ast300_OBS_Shell
- CONF_chopper_ast_OBS_Shell
PACS_Chopper_EnDis_PlateauTest_ast_OBS_Shell
1.3. Chopper Controller Optimisation
2. Further IST Procedures
[http://wiki.mpe.mpg.de/Herschel/PACS/FM_ILT_Procedures/MPIAprocedures#head-db38f31a8bb8d59fdf4cff269aa936e0b3ad201c "Further FM IST Procedures"]